6000 m3/day, Bandar Abbas Refinery

6000 m3/day, Bandar Abbas Refinery

Basic Information

  • Capacity: 6000 m3/day
  • Client: PIDEC
  • Project Manager: Eng. Anosheh Niazi

Key Data

  • Contract date: 2008
  • Commissioning date:-

Technical Information

  • GOR: 8.3
  • TSD: less than 10 ppm
  • Shell material: S.S 316L
  • Tubes material: Ti/Al bras
  • Number of units: 1

Plant Information

  • Location: Bandar Abbas Refinery
  • Status: Under Installation
  • Application: Bandar Abbas Refinery
  • End User: Petrochemical Industries Design and Engineering Company (PIDEC)
12000 m3/day, Bandar Abbas Refinery

12000 m3/day

Basic Information

  • Capacity: 3×4000 m3/day (12000 m3/day)
  • Client: PERSIAN GULF STAR OIL COMPANY (PGSOC)
  • Project Manager: Eng. Anosheh Niazi

Key Data

  • Contract date: 2008
  • Commissioning date:-

Technical Information

  • GOR: 7
  • TSD: less than 10 ppm
  • Shell material: S.S 316L
  • Tubes material: Ti/Al. Bras
  • Number of units: 3

Plant Information

  • Location: Bandar Abbas Refinery
  • Status: Under Installation
  • Application: Bandar Abbas Refinery
  • End User: PERSIAN GULF STAR OIL COMPANY (PGSOC)
4000 m3/day, Qeshm Island

4000 m3/day, Qeshm Island

Basic Information

  • Capacity: 2×2000 m3/day (4000 m3/day)
  • Client:Iranian Offshore Oil Company (IOOC)
  • Project Manager: Mr. Zanjani

Key Data

  • Contract date: 2008
  • Commissioning date: 2011

Technical Information

  • GOR: 7
  • TSD: Less than 10 ppm
  • Shell material:
  • Tubes material:
  • Number of units: 2

Plant Information

  • Location: Qeshm Island
  • Statues: Complete
  • Application:
  • End User: Iranian Offshore Oil Company (IOOC)
4560 m3/day, Kish Island

4560 m3/day, Kish Island

Basic Information

  • Capacity:2×2280 m3/day (4560 m3/day)
  • Client: OMRAN SAHEL
  • Project Manager:

Key Data

  • Contract date: 2010
  • Commissioning date:-

Technical Information

  • GOR: 7.6
  • TSD: Less than 10 ppm
  • Shell material:
  • Tubes material:
  • Number of units: 2

Plant Information

  • Location: Kish Gas Field Development
  • Statues: Under Construction
  • Application:
  • End User: Petroleum Engineering & Development Company (PEDEC)
7500 m3/day, Assaluyeh,

7500 m3/day, Assaluyeh, Mobin Petrochemical Complex

Basic Information

  • Capacity: 7500 m3/day
  • Client: Mobin Petrochemical Company
  • Project Manager: Eng. Mehrdad Ali Ahmad

Key Data

  • Contract date: 2012
  • Commissioning date:-

Technical Information

  • GOR: 8.4
  • TSD: less than 10 ppm
  • Shell material: Duplex
  • Tubes material: Ti/Al Bras
  • Number of units: 1

Plant Information

  • Location: Assaluyeh, Mobin Petrochemical Complex
  • Status: Installation
  • Application: Desalinated Water for Petrochemical Utilities
  • End user: Mobin Petrochemical Complex
6900 m3/day, Tonbak (Phase 12),Assaluyeh

6900 m3/day, Tonbak (Phase 12),Assaluyeh

Basic Information

  • Capacity: 3X2300 m3/day (6900 m3/day)
  • ClientSazehDaelimKayson J.V
  • Project Manager: Eng. A.M Memarzadegan

Key Data

  • Contract date: 2011
  • Commissioning date: –

Technical Information

  • GOR: 8
  • TSD: less than 10 ppm
  • Shell material: Duplex S.S
  • Tubes material: Ti/Al . Bars
  • Number of units: 3

Plant Information

  • Location: Tonbak (Phase 12),Assaluyeh
  • Status: Under Construction
  • Application: South Pars Gas Refinery Phase 12
  • End UserP.O.G.C
(Phases 22-24), Assaluyeh

16000 m3/day South Pars Gas Field Development (Phases 22-24), Assaluyeh

Basic Information

Key Data

  • Contract date: 2011
  • Commissioning date: –

Technical Information

  • GOR: 8
  • TSD: less than 10 ppm
  • Shell material: S.S 316L
  • Tubes material: Ti/Al . Bars
  • Number of units: 4

Plant Information

  • Location: South Pars Gas Field Development (Phases 22-24),Assaluyeh
  • Status: Under Construction
  • Application: South Pars Gas Refinery for Phase 22-23-24 & 13
  • Project Name:
  • End UserP.O.G.C